Progress at the new Kowalski's Market in Excelsior continues to move forward at a great pace! This week's post shows the brick laying is almost finished with just the back sides of the tower need completing. The exterior walls will begin receiving EIFS (Exterior Insulation Finishing System), window frames and glass next week as well. On the interior, the interior walls in the basement are framed and gypsum board is up. The main level walls are also framed and ready for finishes. The electrical contractors have roughed-in throughout and the plumbing is roughed-in on the basement level. The schedule to turn over the site to the owner is July 1st and the project is on track for a late July opening. As always, special thanks to EFH General Contractor for their hard work on site.